Rs 6000 crore ammonia-urea unit commissioned: 2.4 mmscmd of extra gas consumption
Jan 03: Ammonia-Urea Brownfield Project 8Cost - Rs 6000 Crore 8Project Event: Commercial production is started from 1 January 2019. Click here for more details Ammonia-Urea Energy Saving Project 8Cost - Rs 200 Crore 8Project Event: The RFQ for EPC contractor has been already released and technical evaluation is completed but price bid is not opened yet, finalization is due in February 2018 in place of December 2018. tender for major equipment and services is likely to be released in February 2019. Click here for more details