Nov 17: NPK Fertilizer Expansion Project 8Cost - Rs 190 crore 8Project Event:The project has elicited the environment clearance but project activities are still on hold due to lack of fund, the project is likely to be activated in January 2020. RFQ for the LSTK contractor is likely to be released in February 2021 Ammonium Sulphate Expansion Project 8Cost - Rs 9 crore 8Project Event: The proposal for the environmental clearance is likely to be granted in December 2020. RFQ for the EPC contractor is likely to be released in Jan 2021. Phosphoric Acid & Sulphuric Acid Greenfield Project 8Cost - Rs 1800 crore EPC contractor bids likely in January now Sulphuric Acid Greenfield Project 8Cost - Rs 50 crore 8Project Event: A review is ongoing in the MoEF, clearance is likely to be elicited in Jan 2021, RFQs for the local contractor as well as equipment supplier are likely to be released in February 2021