Jul 06: NPK-TSP-GSSP Greenfield Project 8Cost - Rs 100 crore 8Project Event: Preliminary work has been activated, EIA studies are ongoing, the proposal for the environmental clearance has been granted in April 2021. and internal discussion is ongoing, RFO for the PMC contractor is likely to be released in September 2021 Click here for more details Sulphuric Acid Expansion Project 8Cost - Rs 100 crore 8Project Event: The company had signed Furnace Fabrica as an EPC contractor, all equipment has reached the site. 99.4 % of construction work has been completed. The pre-commissioning is ongoing, commissioning is likely to be completed in August 2021, due to the impact of the second wave of Covid-19 Click here for more details