All content in this website is sourced legitimately

Page No: 1
Software update: Update on Ammonium Nitrate project
Jul 19: Ammonium Nitrate Melt Greenfield Project
8Cost - Rs 88 crore
 
8Project Event: The Letter to bid for the LSTK contractor is already out and the bid due date has been extended from 16 July to 6 August 2021. and the scope of work is process licence, supply of basic design, detailed engineering, HAZOP studies and implementation of its recommendation, Procurement, and supply of all equipment, procurement and supply of spares as per spares philosophy mentioned in technical part and more.
Click here for more details


**********************************