Jul 21: DAP Greenfield Project
8Cost - Rs 200 crore
8Project Event: The proposal for the term of references has been accepted and studies are still ongoing, proposal for the environmental clearance is likely to be submitted in August 2021. The company has applied for a loan, RFQ for the EPC the contractor is likely to be released at the end of September 2021.
Click here for more details
Phosphoric acid Expansion Project   
8Cost - Rs 50 crore
8Project Event: The proposal for the term of references has been accepted and the final EIA report preparation is still ongoing, a proposal for environmental clearance is likely to be submitted in August 2021. The company is planning to hire a local contractor. RFQ for the Contractor is likely to be released in September 2021.
Click here for more details


**********************************