Jul 22: NPK Fertilizer Expansion Project 8Cost - Rs 190 crore 8Project Event: The project has been elicited environmental clearance in September 2019, The project activities are still on hold due to lack of funds, the project is likely to be activated in Q2-3 FY 2021. RFQ for the LSTK contractor is likely to be released in October 2021 Click here for more details Ammonia and Captive Power Unit Greenfield Project 8Cost - Rs 1920 crore 8Project Event: The project has elicited the terms of references, The final EIA report preparation is still ongoing, it is likely to be completed in August 2021. The proposal for the environmental clearance is likely to be submitted in August 2021. RFO for the EPC contractor is likely to be released in October 2021. Click here for more details