Oct 19: Effluent Treatment Plant Up-gradation Project 8Cost - Rs 101 crore 8Project Event: All the procurement work has been completed, a long lead item is likely to be reached to the plant in November 2021, Ionexchange India Ltd is the LSTK contractor. Construction is likely to be started in November 2021 Click here for more details Ammonia-Urea Energy Saving Project 8Cost - Rs 481 crore 8Project Event: 99.8 % of the construction has been completed. Testing is ongoing, Project is likely to be completed at the end of October 2021. Click here for more details