Aug 10: Ammonia-Urea Energy Saving Project       
8Cost - Rs 347 Crore
8Project Event: NIT for LSTK contractor has been released and it is likely to be finalized in November 2018.
Click here for more information  
Single Super Phosphate Expansion Project    
8Cost - Rs 35 Crore
8Project Event: The amendment has submitted for the environmental clearance, Tender for Contractor is likely to be released in September in place of July 2018.