Ammonia brownfield project: RFQ for process licencor in Q2, 2019
Oct 08: Ammonia Brownfield Project       
8Cost - Rs 250 Crore
8Project Event: The project is in the initial phase and discussion is ongoing, RFQ for the process licensor is likely to be released in Q2 2019.
Click here for more information
Ammonia-Urea Energy Saving Project      
8Cost - Rs 217 Crore
8Project Event: The project has been signed all the agreement with Siemens for the long lead items and it will take 5 to 6 months to deliver. Construction is likely to be started in April 2019.
Click here for more information

SSP Brownfield Project         
8Cost - Rs 20 Crore
8Project Event: The proposal for the environmental clearance has been accepted and the tender for the EPC contractor is likely to be released in November in place of August 2018.
Click here for more information


**********************************