Ammonia-Urea Energy Saving Project : Civil work is ongoing
Oct 12: Ammonia-Urea Energy Savnig Project       
8Cost - Rs 200 Crore
8Project Event: The basic engineering and detail engineering have been done by KBR and Tecnimont. Erection of NG lines for reformer, boiler & dual burner for auxiliary boiler has been completed. The purchase of a long lead item is ongoing. Land soil testing has been completed for a 200 MTPD LNG Facility and civil construction is ongoing.