Oct 22: Phosphoric Acid Expansion Project 8Cost - Rs 1100 Crore 8Project Event: Detailed engineering is ongoing, RFQ for the long lead item is likely to be released in January 2019. The project has been delayed and the commissioning month has been extended from August 2019 to December 2019. Click here for more details Sulphuric Acid Expansion Project 8Cost - Rs 100 Crore 8Project Event: The EPC contractor has already been selected and construction work is ongoing, Equipment and services contracting is ongoing. Commissioning is likely in July 2019. Click here for more details SSP Greenfield Project 8Cost - Rs 10 Crore 8Project Event: Equipment purchase work is ongoing, RFQ for raw materials is likely to be released in Q4 2018 Click here for more details