Oct 25: DAP Expansion Project 8Cost - Rs 442 Crore 8Project Event: The environmental clearance has already been elicited and details engineering is ongoing. The purchase of long lead item and services is ongoing from May 2018, Construction work is likely to be started from November 2018. Click here for more details Ammonia-Urea Energy Saving Project-II 8Cost - Rs 234 Crore 8Project Event: The project is in the initial phase and RFQ for the LSTK contractor is likely to be released in January 2019. The project is likely to be completed in March 2020. Click here for more details Sulphate of Potash-Bromine and Captive Power Unit Expansion Project 8Cost - Rs 500 Crore 8Project Event: The project is in the initial phase and management is taking time to move forward, The RFQ for the EPC contractor is likely to be released in December 2018. Click here for more details