All content in this website is sourced legitimately

Page No: 1
Software updates: Fertilizer Projects
Jan 08: Ammonia-Urea Brownfield Project
8Cost - Rs 6000 Crore
8Project Event: The purchase of major equipment and services is ongoing and finalization of Civil and Structural works for Main Utility & SILO Substation  is due. Price bid has been opened for Effluent Treatment Plant and Sewage Treatment plant, and finalization is due in January 2019. Tender for Supply and Erection for Electrical and Instrumentation works for Offsite and Utilities has been out and bid due date is 28 January 2019.
Click here for more details
Ammonia-Urea Energy Saving Project
8Cost - Rs 200 Crore
8Project Event: Detailed engineering has been done by KBR and Tecnimont. Erection and installation of mechanical equipment are ongoing. The project is likely to be commissioned in June 2019.
Click here for more details
Ammonium Sulphate Expansion Project

8Cost - Rs 9 Crore
8Project Event: The public hearing has been completed. RFQ for the EPC contractor is likely to be released in February 2019 in place of January 2019.
Click here for more details
 Details

**********************************

Back  |  Top