Nov 08: Ammonia-Urea Energy Saving Project
8Cost - Rs 250 crore
8Project Event: The feasibilty studies are ongoing, RFQ for the process licensor as well as LSTK contractor is likely to be released in December in place of November 2019, due to delay in the discussion.
Sulphuric Acid and Captive Power Unit Expansion Project

8Cost - Rs 300 crore
8Project Event: Project activities are likely to start in January 2020 now, RFQ for the EPC contractor is likely to be released at the end of February 2020.