Software Update: Energy Saving Project Update
Jan 03: Ammonia-Urea Energy Saving Project
8Cost - Rs 250 crore
 
8Project Event: The feasibility studies are ongoing, this is likely to be completed at the end of Feb 2020. RFQ for the process licensor as well as LSTK contractor is likely to be released in March 2020.
Click here for more details
Ammonia-Urea Energy Saving Project 
8Cost - Rs 200 crore
8Project Event: Basic engineering and detailed engineering were done by KBR and Tecnimont. 98 % erection and installation of mechanical equipment has been completed. The project is in the initial phase of commissioning, The commissioning is delayed by four months due to lack of gas connectivity at the site. Commissioning is likely to be completed by March 2020
Click here for more details
  


**********************************