Jan 15: Process Air Compressor Greenfield Project
8Cost - Rs 347 crore
8Project Event: The project is still on hold due to some technical issues, the hiring process of LSTK contractor is also on hold. The project is likely to activated in April 2020.
Click here for more details
Ammonia-Urea Energy Saving Project
8Cost - Rs 380 crore
8Project Event: The Company will be undertaking significant debt-funded capex to meet energy consumption norms applicable under NUP-2015 from FY2021 onwards. The company was under shutdown for economic reasons but now project work is expected to gain speed. Contractor finalization is expected in March 2020.
Click here for more details


**********************************