Software update: Fertilizer projects
Jul 07: Ammonia-Urea Energy Saving Project
8Cost - Rs 250 crore
8Project Event: All project activities are on hold due to COVID-19, the meeting for the project progress is likely to be organized in September 2020. RFQ for the LSTK contractor,it is likely to be released in October in place of April 2020.
Click here for more details
Ammonia-V Revamp Project
8Cost - Rs 50 crore
8Project EventThe detail engineering has been completed. The company is also hired a PMC. The material indenting process is ongoing, NIT for the ammonia wash column and ammonia chiller knock out drum and surge vessel,  as well as hot water preheater and syngas interstage chiller and ammonia chiller has been canceled due to the lockdown. The company is planning to re-release the tender for this equipment in August 2020. The commissioning will see a delay.
Click here for more details


**********************************