Oct 29: Energy Saving-cum- Ammonia-Urea Expansion Project 8Cost - Rs 540 Crore 8Project Event: Tender for critical equipment is already released in February 2018. Technical evaluation has been completed for the long lead item,. These items take a minimum four to six months to deliver. Construction work is likely to be started in Q1 2019. Click here for more details Phosphoric Acid Greenfield Project 8Cost - Rs 10 Crore 8Project Event: The proposal for the environmental clearance was submitted in June 2018, Public hearing has been completed and proposal for the environmental clearance is likely to be elicited in September 2018. The hiring process is ongoing for an EPC contractor. Click here for more details Single/Triple Super Phosphate Greenfield Project 8Cost - Rs 30 Crore 8Project Event: The proposal for environmental clearance was submitted in June 2018, and proposal accepted by SEAC, selection process of EPC contractor is ongoing. Click here for more details